Current Construction Packages 

Terminal

The Terminal and Specialty Services (TSS) contract was awarded to Multiplex in June 2021. Multiplex will deliver the main airport terminal, apron and airport facilities to accommodate up to 10 million passengers per year. It will design and construct all works within the terminal precinct including the terminal building, plaza, connections to the Metro rail station, bus station, taxi ranks, carparks, roads, footpaths and external ancillary buildings and services. 

Head here for any procurement enquires:

HOME | Building WSI T1

Aerial of Terminal Building, December 2023

Airside 

The Airside Civil and Pavement Works package (ACP) was awarded to the CPB ACCIONA Joint Venture in September 2021. This package involves the design and construction of the airside services and utilities which includes runway and taxiway pavements, aircraft pavement markings, airside roads, surface water drainage, aeronautical ground lighting systems, airside security fence and landscaping.     

For any procurement enquiries, please contact The CPB Acciona Joint Venture:

wsaacpsupply@cpbaccjv.com.au

 

End of Runway, December 2023

Landside 

The Landside Civil and Building Works package (LCB) was awarded to AeroWest, a joint venture between BMD Constructions and Seymour Whyte Constructions in December 2021. This package involves the design and construction of carparks, roads, bridges, utilities connections, landscaping and more.

For any procurement enquiries, please contact AeroWest:

procurement@aerowest.com.au

Aeriel of Main Access Road, November 2023

 

Completed Construction Packages 

Early Earthworks 

The Early Earthworks package was delivered by the CPB Contractors and Lendlease Joint Venture and was completed in May 2020. Early earthworks helped lay the foundations for the construction of the airport, including moving 1.8 million cubic metres of earth within a prescribed area of the site, construction of a new and realigned Badgerys Creek Road, and a new intersection at Elizabeth Drive in collaboration with Transport for NSW.

 

Major Earthworks 

The Major Earthworks contract was awarded to CPB Contractors and Lendlease Joint Venture in August 2019. On 9 September 2020, Acciona completed the acquisition of Lendlease Engineering and as such, the Major Earthworks contractor is now referred to as CPB Contractors and Acciona Joint Venture. The major earthworks stage involved significant design and construction responsibilities, including moving around 25 million cubic meters of earth to support construction of the major elements of the airport, such as the runway and terminal. Major Earthworks for Western Sydney International (Nancy-Bird Walton) Airport began in March 2020 and reached practical completion in March 2023. 

 

Adams and Anton Roads Upgrade

Western Sydney Airport (WSA) upgraded a section of Adams Road closest to The Northern Road and all of Anton Road, Luddenham. Works were completed by WSA's Major Earthworks contractor, the CPB Acciona Joint Venture. The upgrade has allowed for heavy vehicles to access the WSA site during construction as well as will provide access when the airport is operational. WSA's upgrade of Adams Road and Anton Road commenced in November 2021 and was completed in November 2022. 

 

WSI Experience Centre

The WSI Experience Centre is now serving as an educational hub for the airport. Building the centre involved detailed excavation and drainage works, building construction of the Experience Centre and the office buildings near it, landscaping and upgrade of Eaton Road. The WSI Experience Centre opened in September 2019 after the completion of works by Watpac Construction.

 

 

Aerial of Site August 2023